Ground Mount Solar Module Racking
Step 2
The Foot is attached at the end of the Standard “Leg” Rail that has not been pre-drilled. Attach one foot to each front leg (shortest Standard Rail lengths) with two Stainless Bolts SPMB3825 per Foot. The Feet are bolted to the Mid Slots of the Standard Rail so the slots of the legs and the feet are positioned to the outside of the array frame.
Step 1






Step 3
Step 4
Step 5
Position the Standard Rails so that the Mid Slots of the Standard Rail face inward. Slide one Stainless Bolt SPMB3845 into each Mid Slot of the Standard Rail and pass the bolt through the specially drilled hole in the leg. Fasten each leg to the Standard Rail with the flat washer, spring washers and nut, in that order for each leg attachment.
Step 6
Step 7
Step 8
Step 9
Step 10
Check that all bolts and clamps are tight and all legs are square. The Ground Mount Array may now be fastened to the supporting structure.